Decision pendingScotland, Scotland
Cato AI data centre, Auchtertool
Application 26/01243/PPP is with Fife Council but stalled: Fife said on 1 April 2026 no EIA was needed, and on 17 August 2026 Scottish Ministers directed that an EIA is required. The applicant must now submit an EIA Report, after which there will be a further public consultation. SEPA has a holding objection on flood risk. [S1] [S2] [S3] [S8]
Key facts
- Status
- Decision pending (application submitted) [S1] [S2] [S3] [S8]
- Decided by
- Fife Council (Scottish Ministers have directed that an EIA is required) [S1] [S2]
- Applicant
- ILI Cato Limited [S5] [S6]
- Developer or backer
- ILI Group (Intelligent Land Investments); part of its 'Stoics' data centre network
- References
- 26/01243/PPP; 25/00552/PAN; 25/03079/SCR
- Location
- Agricultural land north-west of Auchtertool village, north of Camilla Road, Gleniston, adjacent to the Mossmorran industrial complex; Hallyards (Camilla) Castle ruins lie within the site [S4] [S5] [S6]
- IT capacity
- 600MW [S6] [S9]
- Site area
- 25 ha [S6] [S9]
- Buildings
- Up to seven buildings plus on-site substation, up to 35m tall [S6] [S9]
- Investment (claimed)
- GBP5bn (claimed by developer) [S6] [S9]
- Cooling and water
- Estimated annual water demand 34,000 cubic metres (as reported by Data Centre Review; originator of figure not clear) [S7]
- Designations
- Auchtertool Linn Local Wildlife Site (partly on site); Camilla Loch SSSI (nearby); Firth of Forth SPA and Loch Leven SPA (in proximity); Hallyards Castle ruins on site (HES declined to designate); Flood storage area on site (SEPA concern) [S1] [S5] [S8] [S10]
- Previous use
- Farmland [S1] [S5] [S8] [S10]
- Environmental assessment
- Council screening 1 April 2026: no EIA. Scottish Ministers' direction of 17 August 2026: EIA required; applicant to be asked to submit an EIA Report, then further consultation. [S1] [S5] [S8] [S10]
- Public objections
- 1200 [S7] [S9] [S12]
Timeline
- 22 March 2025Proposal of application notice 25/00552/PAN agreed (APRS) [S4]
- 10 November 2025EIA screening request 25/03079/SCR submitted [S4] [S5]
- 1 April 2026Fife Council issues screening opinion: no EIA required [S4] [S5]
- 3 June 2026Planning permission in principle application 26/01243/PPP reported filed (DCD article date) [S6]
- 1 July 2026Historic Environment Scotland response reported (village website); HES declined to schedule Hallyards Castle because proposals are at an advanced stage [S13] [S10]
- 16 July 2026SEPA lodges holding objection on flood risk (Herald report dated 16 July; Fife Today 17 July) [S8]
- 24 July 2026Public comment deadline (one village page also cites 2 July: see conflicts) [S7] [S13]
- 17 August 2026Scottish Ministers issue EIA direction; Fife Council announces it [S1] [S2]
- 4 September 2026Campaigners demonstrate at Scottish Parliament; Deputy First Minister declines a moratorium [S12]
- 16 September 2026Scottish Parliament votes that no hyperscale planning decisions be made until national guidance is complete [S14]
- 17 September 2026Ministers' EIA direction for all data centres over 50MW comes into force [S15]
Statutory consultees
| Body | Position | Date | Detail |
|---|---|---|---|
| SEPA | holding objection | 16 July 2026 | Lack of flood risk information; site's flood storage area would be relocated without demonstrated equivalence; deferral of determination requested. No later withdrawal found. [S8] |
| Historic Environment Scotland | no objection | 1 July 2026 | Declined to schedule Hallyards Castle because development proposals are at an advanced stage. This is a designation decision, not a consultation position: wording of its planning response not seen. [S10] [S13] |
Politicians and organisations
- Mark Ruskell MSP (Scottish Greens) called the no-EIA screening 'unfathomable'
- David Torrance MSP (Kirkcaldy) joined Parliament demonstration
- Auchtertool Community Council (called proposal 'ill-conceived and inappropriate'; asked Environmental Rights Centre Scotland about a legal challenge)
- Auchtertool Action Group
- APRS
Claims
Claims by developers, campaigners or councils, recorded as claims and not checked as fact.
- ILI Group (as reported by Data Centre Review) (developer): GBP5bn investment; about 120 permanent skilled jobs; GBP105m Fife construction GVA [S6] [S7]
- APRS and petition author (campaigners): Would use 4,000-4,200 GWh a year, about 20% of Scotland's total energy consumption [S4] [S11]
- ILI Group (as reported) (developer): Will fully excavate and archaeologically record Hallyards Castle before construction [S10]
Campaigns
- Stop the proposed AI data centre near Auchtertool, Fife (10,605 signatures)
- Say No to Cato
- Auchtertool Community Council data centre page
- APRS Auchtertool page
Sources
- [S1] Environmental Impact Assessment required for proposed Auchtertool data centre. Fife Council, 17 August 2026. Level 1 source.
- [S2] Data centre planning direction. Scottish Government, 17 August 2026. Level 1 source.
- [S3] Scottish Government decision on Fife AI data centre will mean delay. Fife Today, 18 August 2026. Level 4 source.
- [S4] ILI Cato, Auchtertool, Fife site page (last verified 23 February 2026). APRS. Level 6 source.
- [S5] Report on the EIA scoping for Auchtertool. APRS, 12 June 2026. Level 6 source.
- [S6] ILI files to develop 600MW Stoic data center in Fife, Scotland. DatacenterDynamics, 3 June 2026. Level 5 source.
- [S7] More than 1,200 objections lodged against 5bn Fife data centre. Data Centre Review, 24 July 2026. Level 5 source.
- [S8] SEPA joins list of over 1000 objections to giant AI data centre in Fife village. Fife Today, 17 July 2026. Level 4 source.
- [S9] Data centre: Fife Council defends EIA decision branded 'appalling' and 'unfathomable'. Fife Today, 5 June 2026. Level 4 source.
- [S10] Fury as 1000-year-old castle refused listed status and to be replaced by data centre. inkl (syndicated report). Level 4 source.
- [S11] Petition: Stop the proposed AI data centre near Auchtertool, Fife. Change.org (James Melville), 8 June 2026. Level 6 source.
- [S12] Fife AI data centre campaigners join demo at Scottish Parliament. Fife Today, 4 September 2026. Level 4 source.
- [S13] DATA CENTRE (village page: application key, deadlines, group). Auchtertool village website. Level 6 source.
- [S14] MSPs reject datacentre moratorium but pause planning decisions. Computer Weekly, 17 September 2026. Level 5 source.
- [S15] Data centres: Chief Planner Letter and EIA Direction. Scottish Government, 16 September 2026. Level 1 source.
- [S16] Data Centre Map (status table, last updated 13 August 2026). APRS, 13 August 2026. Level 6 source.
- [S17] What did and didn't happen about AI datacentres at Holyrood. Bella Caledonia, 20 September 2026. Level 6 source.