Early stageNorth East, England
Blyth Data Centre, Factory Road, Cambois (TBC Partners)
TBC Partners has asked Northumberland County Council for an EIA screening opinion on a data centre of up to 300MW (developer figure) on about 12 ha at Factory Road, Cambois. The request was listed by the Gazette on 17 August 2026 and reported by DCD on 18 August 2026. No full planning application has been found and no screening decision has been found. [F1] [F2] [F3] [F4]
Key facts
- Status
- Early stage (screening or scoping) [F1] [F2] [F3] [F4]
- Decided by
- Northumberland County Council [F1] [F2] [F3]
- Applicant
- TBC Partners (a UK joint family office) [F1] [F4] [F6]
- References
- Council reference for the EIA screening opinion request not found. The Gazette lists it as 'Land At Factory Road Cambois Northumberland - Screening opinion for a proposed data centre development' (17 August 2026).; TJEC8RQS0MK00 (given by DCD as 'application reference'; this is a planning.org.uk document key of the same type as the Wansbeck record, NOT a council application number)
- Location
- Land at Factory Road, Cambois, south east Northumberland: about 12 ha (developer, via DCD and Baxtel) of former GlaxoSmithKline pharmaceutical site (operated 1971-2004, demolished 2009-2013), now used for aggregate, timber and machinery storage. Alongside the A189, immediately south of the River Wansbeck. Adjacent to the separate Wansbeck Regeneration (West Sleekburn) land and about a mile north of the QTS Cambois site (DCD). [F1] [F2] [F3] [F4]
- IT capacity
- 300MW [F1] [F2] [F4]
- Site area
- 12 ha [F1] [F2] [F4]
- Buildings
- One or two main data centre buildings covering 2.5 to 3.7 ha at about 30 m high, with an on-site substation (layout still being considered) [F1] [F2] [F4]
- Cooling and water
- Closed-loop air-cooled conditioning plant to reduce water consumption, with waste heat applications to be explored (developer's screening documents as reported by DCD) [F1] [F6]
- Previous use
- Former GlaxoSmithKline pharmaceutical manufacturing site; buildings demolished 2009-2013; now storage of recycled aggregate, timber and plant [F1] [F2]
- Environmental assessment
- EIA screening opinion requested from Northumberland County Council; decision not found [F1] [F2]
Timeline
- 2025-01TBC Partners says it launched UK data centre development in January 2025, starting two 300MW projects (it names Didcot and Blyth) and securing 300MW demand connections at both sites (developer's own statement). [F6]
- 17 August 2026Northumberland Gazette lists 'Land At Factory Road Cambois' screening opinion for a proposed data centre among 13 new planning applications, and reports the plans as a third data centre in south east Northumberland. [F2] [F3]
- 18 August 2026DCD reports TBC Partners' screening opinion request for the 'Blyth Data Centre': up to 300MW, about 12 ha, one or two buildings, construction about 24 months, operations 2030-2035. [F1]
- 19 August 2026Gazette reports local residents calling for a pause on the QTS, West Sleekburn and Factory Road schemes. [F7]
- 9 September 2026MP Ian Lavery raises the three Cambois-area schemes at Prime Minister's Questions and asks for a pause; the PM declines a moratorium. [F8]
Politicians and organisations
- Ian Lavery MP (Blyth and Ashington) asked the Prime Minister on 9 September 2026 to pause further development in Blyth and Ashington (names Factory Road among three schemes)
- Northumberland County Council deputy leader Richard Wearmouth criticised speculative data centre developers generally (Gazette; not specific to TBC Partners)
- North East Mayor Kim McGuinness: 'people over infrastructure' (24 September 2026; Factory Road not mentioned)
- Newbiggin Environmental Network, Foxglove and Global Action Plan are named by LBC as campaign groups in the area (article undated in extract; not specific to Factory Road)
Claims
Claims by developers, campaigners or councils, recorded as claims and not checked as fact.
- TBC Partners (screening documents, as reported by DCD and the Gazette; the Gazette says MW not specified in the application materials it saw) (developer): Up to 300MW; closed-loop air cooling; operations 2030-2035 [F1] [F2]
- Local residents quoted by LBC and the Northumberland Gazette (campaigners): Cambois area is becoming a 'dumping ground for data centres'; call for a pause to let locals understand the impact (water, noise, jobs evidence) [F7] [F9]
Campaigns
- Residents' weekly leafleting outside the QTS site and call for a pause on all three Cambois-area schemes
- Protect the Wild open letter against rapid AI data centre expansion
Sources
- [F1] Application filed for data center campus near QTS' site in Northumberland, UK. DatacenterDynamics, 18 August 2026. Level 5 source.
- [F2] Plans emerge for third data centre in south east Northumberland. Northumberland Gazette, 17 August 2026. Level 4 source.
- [F3] Potential new data centre among 13 new planning applications in Northumberland. Northumberland Gazette, 17 August 2026. Level 4 source.
- [F4] Data Center Campus Proposed Near QTS Site in Northumberland, UK. Baxtel. Level 7 source.
- [F5] Application filed for data center campus near QTS' site in Northumberland, UK (syndicated). bebeez, 18 August 2026. Level 7 source.
- [F6] TBC Partners (company website). TBC Partners. Level 3 source.
- [F7] Campaigners call for a pause on Cambois data centre plans amid environmental concerns. Northumberland Gazette, 19 August 2026. Level 4 source.
- [F8] MP urges Prime Minister to block further data centre developments in Blyth and Ashington. Northumberland Gazette, 9 September 2026. Level 4 source.
- [F9] 'Dumping ground for data centres': locals 'extremely worried'. LBC. Level 4 source.
- [F10] Mayor vows to put residents ahead of 'big tech' amid concerns about data centre overdevelopment. Northumberland Gazette, 24 September 2026. Level 4 source.
- [F11] Data centre developers warned they can 'clear right off' amid lack of engagement over plans in Northumberland. Northumberland Gazette. Level 4 source.