Approved - but it's not overYorkshire and the Humber, England
Humber Tech Park, South Killingholme
Planning committee approved outline permission on 31 July 2024, with no votes against and subject to a s106 agreement. Press and the developer describe permission as granted in August 2024. No reserved matters application or construction was found, though the developer says reserved matters are 'underway'. [S1] [S2] [S3] [S4] [S5] [S7]
Key facts
- Status
- Approved - but it's not over (approved) [S1] [S2] [S3] [S4] [S5] [S7]
- Decided by
- North Lincolnshire Council [S1]
- Applicant
- Humber Tech Park Ltd [S1] [S3] [S7]
- Developer or backer
- Greystoke Land (leadership affiliated; shares directors with Elsham Tech Park Ltd per DCD)
- References
- PA/2024/584; PA/SCR/2024/2
- Location
- 75.8 ha of predominantly arable greenfield land south of the A160, South Killingholme, North Lincolnshire, about 4km west of the Humber Estuary; three gas pipelines cross the site. [S1]
- IT capacity
- 384MW [S1] [S2] [S3] [S6]
- Site area
- 75.8 ha [S1] [S2] [S3] [S6]
- Buildings
- Up to three data centre buildings plus a 28,000 sq m glasshouse and substation [S1] [S2] [S3] [S6]
- Investment (claimed)
- GBP2.2bn (Grimsby Live, 2024) to GBP3bn (developer and trade press) [S1] [S2] [S3] [S6]
- Backup generators
- Emergency generators and fuel storage included in the application description; number not captured. [S1] [S3] [S7]
- Cooling and water
- District heating unit supplying waste heat to a horticultural glasshouse (developer claim). Anglian Water: no objection, phasing condition. [S1] [S3] [S7]
- Designations
- Humber Estuary SPA/Ramsar about 4km east (functionally linked land evidence required by Natural England); Flood Zone 1; Archaeological potential (Iron Age/Romano-British) [S1] [S6]
- Previous use
- Arable farmland (greenfield) [S1] [S6]
- Environmental assessment
- Screening reference PA-SCR-2024-2 reported by DCD; outcome not captured. [S1] [S6]
- Public objections
- 119 [S1] [S2] [S3]
Timeline
- 20 March 2024Plans reported as 384MW, 75.8 ha, three buildings (DCD, screening ref given as PA-SCR-2024-2). [S6]
- 31 July 2024North Lincolnshire planning committee approves outline PA/2024/584, no votes against, subject to s106 (GBP12.5m education, plus recreation, health, transport). Officer report listed an archaeology holding position requiring evaluation before determination. [S1] [S2]
- 2 August 2024DCD reports approval (publication date). [S3]
- 6 August 2024Council press release and Place Yorkshire report 'green light' / permission approved (publication date; implies decision notice issued, not confirmed). [S4] [S5]
Statutory consultees
| Body | Position | Date | Detail |
|---|---|---|---|
| National Highways | no objection | 12 July 2024 | Subject to conditions [S1] |
| Environment Agency | no objection | 23 May 2024 | Condition requested [S1] |
| Anglian Water | no objection | 21 May 2024 | Phasing condition recommended [S1] |
| Natural England | no objection | 18 July 2024 | After additional bird survey information [S1] |
| Cadent Gas | objection withdrawn | 23 May 2024 | Withdrawn after dialogue [S1] |
| Archaeology adviser | holding objection | Field evaluation recommended before determination; resolution before the decision not confirmed [S1] |
Claims
Claims by developers, campaigners or councils, recorded as claims and not checked as fact.
- Humber Tech Park / Greystoke as reported by pbctoday, Place Yorkshire (developer): About 370 to 400 permanent jobs at about GBP50,000 average salary; GBP3bn investment; 2,500 to 3,500 construction jobs a year [S5] [S8]
- Applicant's agent at committee, as reported by Grimsby Live (developer): Granting permission will increase food production because of the heated glasshouse [S2]
- Two residents who spoke against at committee (other): Noise from cooling 24/7 will be heard over a large area and affect health; loss of 200 acres of productive farmland [S2]
Sources
- [S1] Planning committee 31 July 2024, application PA/2024/584 (report). North Lincolnshire Council, 31 July 2024. Level 1 source.
- [S2] Decision made on GBP2.2bn data centre near South Killingholme. Grimsby Live, 31 July 2024. Level 4 source.
- [S3] Green light for 386MW data center campus in Lincolnshire, UK. DatacenterDynamics, 2 August 2024. Level 5 source.
- [S4] Lincolnshire council approves new data centre campus, Humber Tech Park. pbctoday, 6 August 2024. Level 4 source.
- [S5] GBP3bn Humber Tech Park clears planning. Place Yorkshire, 6 August 2024. Level 4 source.
- [S6] 384MW data center campus proposed in North Lincolnshire, UK. DatacenterDynamics, 20 March 2024. Level 5 source.
- [S7] Greystoke: Data Centres (Humber Tech Park). Greystoke Land. Level 3 source.
- [S8] Humber Tech Park (developer website). Humber Tech Park. Level 3 source.