South Gyle data centre (1 Redheughs Avenue, former RBS headquarters site)

Councillors refused planning permission in principle on 4 February 2026; the developer appealed. On 30 July 2026 the DPEA issued a screening direction that an EIA is required, the appellant confirmed on 12 August that it will submit an EIA Report, and on 17 August 2026 Scottish Ministers recalled the appeal to decide it themselves. The case is on hold; no EIA Report or Ministers' decision had been found by 3 October 2026. [S1] [S2] [S3]

Key facts

Status
Refused - now at appeal (appeal lodged) [S1] [S2] [S3]
Decided by
Scottish Ministers (appeal recalled from the DPEA reporter on 17 August 2026) [S1] [S2] [S5]
Applicant
Shelborn Drummond Ltd [S1] [S5]
Developer or backer
Shelborn (spelt 'Shelburn' and 'Shelborne' in some press); landowner/applicant per Edinburgh News
References
25/04239/PPP; 25/03575/SCR; PPA-230-2794
Location
Former Royal Bank of Scotland headquarters site at Redheughs Avenue, South Gyle / Edinburgh Park, west Edinburgh. Edinburgh News calls it the 'Edinburgh Park' site. [S1] [S3] [S7]
IT capacity
212.42MW [S7] [S4]
Backup generators
About 200 diesel backup generators (reported as the basis of the reporter's concern); campaigners compare this to '100,000 idling cars-worth of diesel'. [S10] [S4] [S6]
Cooling and water
Council refusal discussion noted air-cooling efficiency not demonstrated and no pre-engagement with Scottish Water on water use (press account of councillors' reasons). [S10] [S4] [S6]
Previous use
Former Royal Bank of Scotland headquarters site; office/mixed-use development area in City Plan 2030 (Place 19, Edinburgh Park) [S1] [S6] [S7]
Environmental assessment
Council screening said no EIA needed. DPEA Screening Direction of 30 July 2026 requires an EIA; appellant confirmed 12 August 2026 it will submit an EIA Report. EIA Report not yet found as at 3 October 2026. [S1] [S6] [S7]

Timeline

  1. 18 August 2025
    Application 25/04239/PPP submitted to City of Edinburgh Council [S1]
  2. 4 February 2026
    Development Management Sub-Committee refuses planning permission in principle, against officer recommendation to approve (unanimous per press). Refusal grounds per APRS: NPF4 policies 1 and 2, and City Plan Place 19 [S3] [S6] [S8]
  3. 9 February 2026
    Council decision recorded on DPEA case page (decision notice date) [S1]
  4. 31 March 2026
    Appeal received by the DPEA [S1]
  5. 30 July 2026
    DPEA issues Screening Direction: EIA required (overturns council screening 25/03575/SCR) [S1]
  6. 4 August 2026
    Data Centre Review reports the EIA ruling (publication date, not ruling date) [S4]
  7. 12 August 2026
    Appellant's agent confirms the appellant will submit an EIA Report [S1]
  8. 17 August 2026
    Scottish Ministers recall the appeal (Re-call Direction); case on hold, DPEA target date shown as 20 November 2026 [S1] [S2]
  9. 16 September 2026
    Scottish Parliament votes that no hyperscale data centre planning decisions be made until national guidance is complete [S15]
  10. 17 September 2026
    Scottish Ministers' EIA direction for data centres over 50MW comes into force [S17]

Politicians and organisations

  • City of Edinburgh Council voted in March 2026 to call for a national moratorium on hyperscale AI data centres (per APRS)
  • Councillor Alys Mumford (Green) questioned the 'green' claim at committee
  • APRS
  • ERCS Legal Ltd (interested party in the appeal, per DPEA case page)
  • The Cockburn Association (published commentary)

Claims

Claims by developers, campaigners or councils, recorded as claims and not checked as fact.

  • Shelborn Drummond Ltd (as described in the DPEA project description) (developer): Proposal is a 'green data centre' with public park, sports facilities and active travel routes [S1]
  • Foxglove (emissions), APRS (household equivalent) (campaigners): Over 200,000 tonnes of greenhouse gas a year, comparable to Edinburgh Airport; electricity use equal to about 500,000 Scottish households [S10] [S11] [S9]
  • As reported from the committee papers by APRS; not checked against the report (other): About 39 staff and 200+ car parking spaces [S8]

Campaigns

Sources

  1. [S1] DPEA case PPA-230-2794, 1 Redheughs Avenue (case page and timeline). Planning and Environmental Appeals Division, Scottish Government, 17 August 2026. Level 1 source.
  2. [S2] Data centre planning direction. Scottish Government, 17 August 2026. Level 1 source.
  3. [S3] Development Management Sub-Committee webcast, Wednesday 4 February 2026 (items 6a and 6b, application 25/04239/PPP). City of Edinburgh Council, 4 February 2026. Level 1 source.
  4. [S4] Rejected Edinburgh data centre needs EIA before appeal, says Scottish Gov. Data Centre Review, 4 August 2026. Level 5 source.
  5. [S5] Scottish Government intervenes over two proposed data centres in Edinburgh. Edinburgh News, 17 August 2026. Level 4 source.
  6. [S6] Controversial Edinburgh data centre plan thrown out by councillors. Edinburgh News. Level 4 source.
  7. [S7] South Gyle (Edinburgh) site page. Action to Protect Rural Scotland (APRS). Level 6 source.
  8. [S8] Edinburgh Data Centre Refused (press release). APRS. Level 6 source.
  9. [S9] Edinburgh Data Centre developers appeal. APRS. Level 6 source.
  10. [S10] Scottish Government rules environmental report needed for Edinburgh AI data centre. inkl (syndicated report), 4 August 2026. Level 4 source.
  11. [S11] Edinburgh Council - require Environmental Impact Assessments for massive new data centres. Foxglove, 9 December 2025. Level 6 source.
  12. [S12] Foxglove campaigns list (first page). Foxglove. Level 6 source.
  13. [S13] Petition: STOP Hyperscale AI DATA CENTRE at Hermiston, Edinburgh. Change.org (Gordon Fraser), 17 March 2026. Level 6 source.
  14. [S14] Petition update: URGENT CALL for the First Minister's Intervention. Change.org (Gordon Fraser), 28 April 2026. Level 6 source.
  15. [S15] MSPs reject datacentre moratorium but pause planning decisions. Computer Weekly, 17 September 2026. Level 5 source.
  16. [S16] Data Centre Map (status table, last updated 13 August 2026). APRS, 13 August 2026. Level 6 source.
  17. [S17] Data centres: Chief Planner Letter and EIA Direction. Scottish Government, 16 September 2026. Level 1 source.
  18. [S18] Green Claims Meet Planning Reality: Lessons from Edinburgh's South Gyle Data Centre Rejection. The Cockburn Association. Level 6 source.