Decision pendingNorth East, England

West Sleekburn Data Centre (Wansbeck Regeneration Ltd)

Wansbeck Regeneration Ltd submitted an outline application (all matters reserved except access) for up to 356,500 sq m of data centre floorspace at West Sleekburn, with documents published on 18 June 2026. It was still under consideration by Northumberland County Council in mid-September 2026. [S1] [S3] [S4] [S8]

Key facts

Status
Decision pending (application submitted) [S1] [S3] [S4] [S8]
Decided by
Northumberland County Council [S3]
Applicant
Wansbeck Regeneration Ltd [S1] [S3]
References
TGQCQFQSMQD00; 70739/01/NW/EC
Location
About 28 ha of agricultural land north-west of High Brocklands, West Sleekburn, south of the River Wansbeck with the A189 to the east; part of land associated with the former GlaxoSmithKline site. About one to two miles from the QTS Cambois site. [S1] [S2] [S3]
IT capacity
50MW [S1] [S2] [S3]
Site area
28 ha [S1] [S2] [S3]
Buildings
Three data centre buildings, two substations [S1] [S2] [S3]
Investment (claimed)
GBP3.8bn to GBP3.89bn (claimed by developer) [S1] [S2] [S3]
On-site generation
Gas power plant described as up to 49.9MW ancillary generation in the application description; DCD and Silicon describe 90MW of natural gas fuel cells as a bridging solution to be removed once fully operational. [S1] [S2] [S3]
Backup generators
Emergency generators using hydrotreated vegetable oil (Non-Technical Summary). [S1] [S2] [S3]
Cooling and water
Developer says private water supply via borehole. Water tank and pump room included. Not independently checked. [S1] [S2] [S3]
Previous use
Agricultural land, formerly part of land linked to the GlaxoSmithKline pharmaceutical site (operational 1971 to 2004, as reported by DCD) [S1] [S2]
Environmental assessment
Environmental Impact Assessment carried out; Environmental Statement and Non-Technical Summary submitted with application. [S1] [S2]

Timeline

  1. 18 June 2026
    Application documents published (planning.org.uk path dated 20260618); Place North East reports 'Plans in'. Press 19 and 23 June 2026 (DCD, Silicon). [S1] [S2] [S3]
  2. 17 August 2026
    Gazette lists a separate Factory Road, Cambois data centre screening opinion among new applications (different applicant, TBC Partners). [S5]
  3. 9 September 2026
    MP Ian Lavery asks the Prime Minister to block further data centres in Blyth and Ashington, naming West Sleekburn. [S6]
  4. 17 September 2026
    Council leader Glen Sanderson says there is 'a limit' to data centres Northumberland can house; West Sleekburn under council consideration. [S8]

Politicians and organisations

  • Ian Lavery MP (Blyth and Ashington): moratorium and Critical National Infrastructure Levy (2026-09-09)
  • Glen Sanderson, council leader: 'a limit' to data centres (2026-09-17)
  • Kim McGuinness, North East Mayor: 'people over infrastructure' (2026-09-24, general)
  • Protect the Wild (cumulative impact letter, 2026-09-30)
  • Informal residents' group (weekly leafleting at QTS site)

Claims

Claims by developers, campaigners or councils, recorded as claims and not checked as fact.

  • Wansbeck Regeneration Ltd (developer): 785 direct full-time jobs and 1,095 indirect (Silicon); construction 665-780 direct jobs and operational 460-640 direct jobs (Gazette/Place NE, from application documents) [S3] [S4]
  • Wansbeck Regeneration Ltd as quoted by Silicon and LBC (developer): Data centres benefit from clustering; private borehole water supply avoids local supply impact; noise below background levels [S4] [S7]
  • Ian Lavery MP (other): Moratorium needed until regulation catches up; community cannot become 'plug-in centre' for the nation's digital needs [S6] [S7]

Campaigns

Sources

  1. [S1] West Sleekburn Data Centre Volume 3: Non-Technical Summary (application 70739/01/NW/EC). Wansbeck Regeneration Ltd via planning.org.uk, 18 June 2026. Level 2 source.
  2. [S2] Plans filed for three-building data center campus in Northumberland, UK. DatacenterDynamics, 19 June 2026. Level 5 source.
  3. [S3] Plans in for West Sleekburn Data Centre. Place North East, 18 June 2026. Level 4 source.
  4. [S4] Plans filed for second major Northumberland data centre. Silicon UK, 23 June 2026. Level 5 source.
  5. [S5] Potential new data centre among 13 new planning applications in Northumberland. Northumberland Gazette, 17 August 2026. Level 4 source.
  6. [S6] MP urges Prime Minister to block further data centre developments in Blyth and Ashington. Northumberland Gazette, 9 September 2026. Level 4 source.
  7. [S7] 'Dumping ground for data centres': locals 'extremely worried'. LBC. Level 4 source.
  8. [S8] Warning there is a 'limit' to the number of data centres Northumberland can house. Northumberland Gazette, 17 September 2026. Level 4 source.
  9. [S9] Northumberland data centres: Wildlife group warns of combined impact on nature. Northumberland Gazette, 30 September 2026. Level 4 source.
  10. [S10] Campaigners call for a pause on Cambois data centre plans. Northumberland Gazette, 19 August 2026. Level 4 source.
  11. [S11] Application filed for data center campus near QTS' site (Factory Road, TBC Partners). BeBeez, 18 August 2026. Level 5 source.